Texas · Data center compliance

Texas data center compliance guide: federal, state and local requirements

Texas data center development is effectively on hold through at least mid-December 2026: Governor Abbott ordered an ERCOT/PUCT audit of every large load in the queue, mandatory water-use reporting and a halt on TCEQ permits for data center projects. At the same time, the PUCT finalized SB 6's large-load interconnection rule.

Updated

Serving Dallas–Fort Worth, Hood & Hill counties, San Marcos / Hays County, Austin & San Antonio and West Texas & Panhandle in Texas.

At a glance

Texas data center rules at a glance

  • Sept. 21, 2026

    TCEQ halts all permits related to data center projects, including off-grid sites

  • $50K/MW

    Financial security for large loads of 75 MW or more under the PUCT's SB 6 rule

  • ~Dec. 10, 2026

    ERCOT/PUCT audit of the large-load queue due

  • June 2026

    San Marcos becomes the first Texas city to ban data centers

Key takeaways for Texas data center projects

  • Texas data centers answer to the PUCT, ERCOT, TCEQ, the Texas Water Development Board, groundwater conservation districts, the Comptroller, TDLR and the State Fire Marshal, plus cities.
  • TCEQ stopped issuing data center permits on Sept. 21, 2026 and will not resume until the ERCOT audit ends; the governor has set six conditions for resuming.
  • The PUCT's large-load rule (Project 58481) requires a $100,000 study fee and $50,000 per MW of security for loads of 75 MW or more.
  • Cities can zone, condition or ban data centers; most counties have little authority beyond floodplain, roads and fire code.
Recent and pending laws

What’s changed for Texas data centers

The rules moving fastest right now. Each entry shows its status and the dates to watch.

  1. Date: Sept. 24, 2026

    Attorney General investigation

    Reviews compliance with TWDB water-use surveys

    Status: Open

  2. Date: Sept. 21, 2026

    TCEQ permit pause

    Halts all permits related to data center projects

    Status: In effect

  3. Date: Sept. 18, 2026

    PUCT large-load rule

    $100K study fee, $50K/MW security, CIAC, minimum billing for 75 MW+

    Status: In effect Oct. 8

  4. Date: Sept. 14, 2026

    TWDB directive

    Mandatory water-use reporting enforcement; joint water audit

    Status: In effect

  5. Date: Aug. 3, 2026

    ERCOT/PUCT audit order

    Audits all large loads in the interconnection queue

    Status: Due ~Dec. 10

  6. Date: June 2025

    SB 6

    Large-load standards, backup generation disclosure, remote disconnect

    Status: Law

Who regulates what

Four layers of oversight on every Texas project

A compliant Texas data center has to clear federal rules, state agency permits, local approvals and utility requirements at the same time.

  • Federal

    • U.S. EPA (air, water, SPCC, EPCRA)
    • U.S. Army Corps of Engineers
    • OSHA
    • FAA
    • FERC / NERC
  • State

    • Public Utility Commission of Texas (PUCT)
    • ERCOT
    • Texas Commission on Environmental Quality (TCEQ)
    • Texas Water Development Board (TWDB)
    • Groundwater conservation districts
    • Comptroller of Public Accounts
    • TDLR / State Fire Marshal
  • Local

    • Cities (zoning, building codes, ETJ rules)
    • Counties (roads, floodplain, fire code)
  • Utility & grid

    • Oncor
    • CenterPoint
    • AEP Texas
    • TNMP
    • Austin Energy and CPS Energy
    • Co-ops
Lifecycle

Texas requirements from site selection to decommissioning

  1. 01

    Site selection

    Confirm city limits and ETJ status, the groundwater district, whether the utility is in ERCOT, and any moratorium or pending AG opinion. Budget for PUCT study fees and security.

  2. 02

    Permitting & construction

    TCEQ air authorizations for generators and on-site power and TPDES construction stormwater (both paused for data centers; stormwater NOIs suspended in October 2026), city building permits and TDLR requirements.

  3. 03

    Operations

    SB 6 obligations, including backup generation disclosure and remote disconnect capability, TWDB water-use reporting, air permit limits and ERCOT large-load requirements.

  4. 04

    Decommissioning

    Close fuel tanks under TCEQ rules, terminate air authorizations, handle batteries and electronics properly and settle utility contract and CIAC obligations.

On your jobsite

What this means on your jobsite

  1. Site selection

    Most site-selection risk shows up later as a construction delay. Test the ground and the history before you close.

    • Soils and foundations

      Expansive clays across much of Central and North Texas drive foundation design and slab performance for heavy equipment rooms.

      You'll need: geotechnical data and early testing to confirm the design assumptions

    • Environmental history

      Lenders and buyers will expect a Phase I environmental site assessment before acquisition, and a Phase II if it flags concerns.

      You'll need: an ASTM-based Phase I in the diligence file

    • City limits and ETJ status

      Inside a city, its adopted building code and special inspection program apply. In unincorporated county land, inspection oversight may fall mostly to you and your insurer.

      You'll need: a decision now on who will act as your independent inspection and testing agency

  2. Permitting & construction

    The TCEQ pause has stopped permits, not the paperwork. Use the wait to get your testing and inspection records ready, so you can start building as soon as permits resume.

    • Special inspections

      Cities that adopt the International Building Code require third-party special inspections of structural concrete, steel, welding and fireproofing.

      You'll need: an approved special inspection agency and daily reports the building official will accept

    • Welds and structural connections

      Structural steel, pipe supports and generator skids need weld inspection and nondestructive testing before they’re covered up.

    • Construction stormwater

      Disturbing an acre or more needs TPDES construction stormwater coverage and a working SWPPP. TCEQ suspended data center stormwater notices of intent in October 2026, so coverage now waits on the pause.

      You'll need: documented inspections throughout the build

    • Generators and fuel

      Backup generators need a TCEQ air authorization, which is currently paused for data center projects, and the fuel storage brings tank rules and a federal SPCC plan.

      You'll need: generator specifications, run-hour limits and tank documentation ready to file

    • Commissioning before energization

      SB 6 and ERCOT large-load requirements put your electrical and backup systems under scrutiny before energization.

      You'll need: commissioning records and integrated systems test results showing the systems perform as designed

  3. Operations

    Once you’re live, compliance becomes a matter of records: who tested what, when, and against which standard.

  4. Decommissioning

    The fastest way to lose value at end of life is a site with undocumented contamination or orphaned tanks.

    • Tank closure

      Fuel tanks must be closed under TCEQ rules, with records of the closure and of any release.

      You'll need: inspection and sampling before the tanks come out

    • Batteries and hazardous materials

      UPS and battery energy storage systems need proper removal, handling and recycling records, as do any EPCRA-reportable chemicals on site.

    • Exit assessment

      A post-operations environmental assessment protects the seller and the next owner.

Key local jurisdictions

Where Texas rules get local

Zoning, noise, water and moratoria vary county by county. Confirm the current ordinance before you file.

  • Dallas–Fort Worth

    Largest Texas cluster; Oncor territory and DFW ozone nonattainment add air scrutiny.

  • Hood & Hill counties

    Unincorporated sites with contested county authority over moratoria.

  • San Marcos / Hays County

    Citywide ban adopted June 16, 2026; projects shift to county land.

  • Austin & San Antonio

    Municipal utilities set their own large-load terms; Edwards Aquifer rules.

  • West Texas & Panhandle

    Large AI campuses with on-site generation, now caught by the TCEQ pause.

How ATS + SGS help

One testing, inspection and certification partner for the whole build

  • Construction & code compliance

    Materials testing, special inspections and nondestructive testing so your Texas build passes inspection the first time.

    • Code compliance
    • NDT inspection
  • Electrical, fire & commissioning

    Electrical and fire protection testing, generator and UPS verification, and commissioning support before go-live.

    • Fire & electrical
    • Commissioning
  • Environmental & due diligence

    Environmental compliance support, technical due diligence for investors and insurers, and ESG assurance.

    • Technical due diligence
    • ESG assurance
FAQ

Texas data center compliance questions

A Texas data center typically needs TCEQ air authorization for its backup generators and any on-site power plant, TPDES construction stormwater coverage, city zoning and building permits if inside city limits, and a large-load interconnection agreement under the PUCT's SB 6 rule. TCEQ has paused issuing data center permits since Sept. 21, 2026.

This page summarizes Texas data center requirements as of October 12, 2026 for general information. It is not legal advice. Confirm current requirements with the relevant agency or counsel before filing.

Bring one TIC partner to your next Texas data center project

Tell us where you're building and what role you play. We'll route you to the right ATS specialist.

Other states

Data center compliance guides by state

Texas

Development is effectively on hold through mid-December 2026: an ERCOT/PUCT large-load audit, mandatory water reporting and a TCEQ permit pause, alongside SB 6's new interconnection rule.